Florida Chapter 558 requires pre-suit notice and a repair opportunity before construction defect claims. Associations over 20 parcels must give 120 days.

Quick Answer

Chapter 558 of the Florida Statutes sets a pre-suit notice-and-repair process that a property owner, including an association, must follow before filing a lawsuit or arbitration over a construction defect. The claimant serves a written notice of claim, the builder or other responsible party gets a chance to inspect and offer to repair or pay, and the claimant must respond to any offer.

For an association "representing more than 20 parcels," the notice must be served at least 120 days before filing, not 60. A lawsuit filed without following the chapter is subject to a stay on timely motion.

At a Glance

ItemDetail
Law/citationFla. Stat. Chapter 558, Construction Defects (ss. 558.001 to 558.005)
Effective dateCreated by chapter 2003-49. The definitions section (558.002) was last amended by section 18 of chapter 2023-203; the notice section (558.004) by chapter 2019-75.
Applies toClaims by property owners, subsequent purchasers and associations (as defined in ss. 718.103, 719.103(2), 720.301(9) or 723.075) against contractors, subcontractors, suppliers and design professionals, for contracts made after October 1, 2009 unless the parties opted out in writing
Key sections558.002 definitions; 558.003 compliance and stay; 558.004 notice, inspection, response; 558.005 application and contract notice
Remedy or penaltyCourt "shall stay the action, without prejudice" until the claimant complies; no fine stated

What the Law Says

Who and what is covered

A "claimant" includes "a property owner, including a subsequent purchaser or association." An "action" means a civil action or arbitration for damages or indemnity for damage to or loss of property from an alleged construction defect. It does not include administrative actions or personal injury claims. A "construction defect" is a deficiency in design, specifications, surveying, planning, supervision, observation of construction, or construction, repair, alteration or remodeling that results from defective materials, a code violation giving rise to a cause of action under s. 553.84, a design that fails professional standards of care, or work that fails "accepted trade standards for good and workmanlike construction." Under 558.005, the chapter applies where the agreement to make the improvement was made after October 1, 2009 and the defect arose after completion of the building or improvement, unless the parties agreed in writing to opt out.

The notice of claim

The claimant must serve written notice referring to the chapter at least 60 days before filing, or at least 120 days before filing for an association representing more than 20 parcels. It must describe each alleged defect "in reasonable detail" and, based on at least a visual inspection, identify the location of each defect. The claimant has "no obligation to perform destructive or other testing." "Service" means certified mail with USPS evidence of delivery or attempted delivery to the last known address, hand delivery, or courier with written evidence of delivery. A notice of claim "shall not toll any statute of repose period under chapter 95."

The response clock

StepStandard claimAssociation with more than 20 parcels
Notice served before filing suitAt least 60 daysAt least 120 days
Inspection by served partyWithin 30 days after serviceWithin 50 days
Served party forwards notice to subcontractorsWithin 10 daysWithin 30 days
Subcontractor written responseWithin 15 days after copyWithin 30 days after copy
Served party's written response to claimantWithin 45 daysWithin 75 days
Claimant accepts or rejects offerWithin 45 days after receiving the offerWithin 45 days after receiving the offer

What the response may say

  • an offer to remedy at no cost, with a detailed description and timetable;
  • an offer to settle by monetary payment that will not obligate the insurer, with a timetable;
  • a combination of repair and payment;
  • a statement that the person disputes the claim and will not remedy or settle; or
  • a statement that a payment, including insurance proceeds, will be determined by the insurer within 30 days.

After the response

If the claim is disputed, or there is no timely response, the claimant "may, without further notice, proceed with an action." If the claimant accepts a repair offer and the offeror fails to perform within the agreed time and manner, the claimant may proceed without further notice. If the offeror performs, the claimant "is barred from proceeding with an action for the claim described in the notice of claim." If the claimant sues without first accepting or rejecting an offer, the court stays the action on timely motion. Offers are not an admission of liability and are not admissible in an action under the chapter.

Inspection, testing and tolling

The claimant must give reasonable access during normal working hours. Destructive testing is by mutual agreement on terms in the statute, including a written description, a list of three qualified testers if the claimant objects, and a requirement that it "shall not render the property uninhabitable." A claimant who refuses reasonable destructive testing has "no claim for damages which could have been avoided or mitigated" had testing been allowed. Serving notice tolls the statute of limitations until the later of 90 days (120 days for associations over 20 parcels) after service or 30 days after the end of the repair or payment period in an accepted offer. The parties may extend by stipulation.

Documents and emergencies

On written request citing the subsection, the parties must exchange within 30 days design plans, specifications, as-built plans, photos and videos, expert reports, subcontracts, purchase orders and maintenance records. A claimant may make "necessary emergency repairs" to protect health, safety and welfare. An arbitration clause that conflicts with the chapter yields to the chapter.

What This Means in Practice

For boards

Our reading: for an association over 20 parcels, the statutory minimum before filing is 120 days from service, but the response and offer-acceptance periods can stretch the practical timeline. Meanwhile the notice does not stop the statute of repose, so counsel should calendar repose separately. See our page on the 2023 statute of repose bill.

For owners

Owners should expect the board to control the notice and any inspection access, since "an association's right to access property for either maintenance or repair includes the authority to grant access for the inspection."

Developer turnover

Section 718.301(7) separately requires that defects alleged by an association against a developer be examined and certified by an appropriately licensed Florida professional. Read the two together; see our turnover page.

What the chapter does not say

  • It creates no new rights or causes of action, and it does not bar or limit existing rights, causes of action or defenses except as the chapter specifically provides.
  • It does not apply to personal injury claims.
  • Whether an association with more than 20 parcels counts only residential parcels, or how "representing" is measured, is not defined in the text we read. Ask counsel.

Timeline

DateEvent
2003Chapter created by chapter 2003-49
October 1, 2009Chapter applies to agreements made after this date unless parties opt out in writing
2019Section 558.004 last amended (chapter 2019-75)
2023Section 558.002 amended by chapter 2023-203, section 18

We did not review whether later bills changed sections other than those listed in the current History lines.

Related Florida Law

Board Checklist

  • Engage counsel and licensed professionals before drafting a notice of claim.
  • Count parcels to determine whether the 120-day or 60-day period applies.
  • Prepare a notice that cites Chapter 558 and describes each defect and its location.
  • Serve by certified mail with USPS record, hand delivery, or courier with written evidence.
  • Calendar the 45-day deadline to accept or reject any offer.
  • Separately calendar any statute of limitations and statute of repose dates.
  • Plan inspection access and any destructive-testing agreement.
  • Preserve plans, photos, expert reports and maintenance records for the document exchange.

Frequently Asked Questions

Do associations have to follow Chapter 558 before suing a builder?

Yes, for claims within the chapter. A suit filed without compliance is stayed on timely motion until the claimant complies.

How long before filing must notice be served?

At least 60 days, or at least 120 days for an association representing more than 20 parcels.

What can the builder do after notice?

Inspect, offer repair, payment or both, dispute the claim, or state that its insurer will decide on payment within 30 days.

Does the notice pause the statute of repose?

No. The statute says a notice of claim "shall not toll any statute of repose period under chapter 95."

Does it pause the statute of limitations?

Yes, for the period described in 558.004(10), generally until the later of 90 days (120 days for larger associations) or 30 days after the repair or payment period.

Are personal injury claims covered?

No. The definition of "action" excludes personal injury claims.

Can the parties change the process?

Yes. They may agree in writing to pre-action mediation or otherwise alter the procedure, or opt out as described in 558.005.

Where This Comes From

We read the full current text and History lines of Fla. Stat. Chapter 558 (ss. 558.001 to 558.005) on the Florida Legislature's Online Sunshine site. The official chapter is at leg.state.fl.us.

How APM Helps

Association Property Managers provides remote HOA and condo management for associations in Florida, starting at a flat $99/month per community with no per-door fees or long-term contracts. See remote management in Florida, browse every Florida state-law guide, or request a free proposal, delivered within three business days. Laws and licensing rules differ by state, and we confirm the requirements for Florida when we build your proposal.

Legal disclaimer: This article is general information, not legal advice. Laws change and associations differ. Confirm the current statute text and how it applies to your governing documents with a licensed Florida attorney before acting.

What Will APM Cost for Your Community?

Adjust the sliders below — your estimate updates instantly.

Number of Homes / Doors
50
10500
Board Meetings per Year
4
112

Facilities & Common Areas

Recommended: Remote Essentials Plan
$12.08/ door / mo
Base rate $12 – $13.20 / door / mo
Est. Monthly
$600 – $604
Est. Annual
$7,200 – $7,248
Homes50
Meetings / yr4
Facilities0

Straightforward communities that mainly need financial tools and dues collection.

Get My Free Proposal →

Free. No obligation. Delivered in 3 business days.

✓500+ communities served✓98% client retention✓No sales call required

Ready to work with Association Property Managers?

Get a free, itemized proposal for your community — delivered within 3 business days.

Request a Free Proposal